The PreMortem - anticipating a plan's weaknesses

By Shawn. Filed in Facilitation, Knowledge, Narrative.

One of the techniques I’ve recently introduced to my lessons-learning projects is what Gary Klein calls a PreMortem. As we all know, a PostMortem helps us learn why a patient has died. A PreMortem explores why a project might die in the future. Here’s how Gary describes the approach. I find it works well at the end of an open space after the planning process is complete. It injects an additional level of realism into the plans.

 

Step 1: Preparation. Team members take out sheets of paper and get relaxed in their chairs. They should already be familiar with the plan, or else have the plan described to them so they can understand what is supposed to be happening.

Step 2: Imagine a fiasco. When I conduct the PreMortem, I say I am looking into a crystal ball and, oh no, I am seeing that the project has failed. It isn’t a simple failure either. It is a total, embarrassing, devastating failure. The people on the team are no longer talking to each other. Our company is not talking to the sponsors. Things have gone as wrong as they could. However, we could only afford an inexpensive model of the crystal ball so we cannot make out the reason for the failure. Then I ask, “What could have caused this?”

Step 3: Generate reasons for failure. The people on the team spend the next three minuted writing down all the reasons why they believe the failure occurred. Here is where intuitions of the team members come into play. Each person has a different set of experiences, a different set of scars, and a different mental model to bring to this task. You want to see what the collective knowledge in the room can produce.

Step 4: Consolidate the lists. When each member of the group is done writing, the facilitator goes around the room, asking each person to state one item from his or her list. Each item is recorded in a whiteboard. This process continues until every member of the group has revealed every item on their list. By the end of this step, you should have a comprehensive list of the group’s concerns with the plan as hand.

Step 5: Revisit the plan. The team can address the two or three items of greatest concern, and then schedule another meeting to discuss ideas for avoiding or minimising other problems.

Step 6: Periodically review the list. Some project leaders take out the list every the list every three to four months to keep the spectre of failure fresh, and re-sensitise the team to the problems that may be emerging. (pp 89–90)

Klein, G. (2003). Intuition at Work: Why Developing Your Gut Instincts Will Make You Better at What You Do. New York, Currency Doubleday.

Send this entry to:     del.icio.us icon StumbleUpon Toolbar Slashdot Digg icon Reddit icon Newsvine icon Searchles icon

email iconEmail this entry to a friend      technorati icon View the Technorati Link Cosmos for this entry

Trackback Pings

TrackBack URL for this entry:
http://www.anecdote.com.au/cgi-bin/mt-tback.cgi/579

Comments

"Pre mortem" - and I've just been reading Philip K Dick's "Minority Report", which talks all about "pre crime" and precognition... Amazing what insights and knowledge you can gain when you simply turn things around…

Posted by: Keith De La Rue at December 15, 2006 9:52 AM

This is a great tool! Thanks for sharing!

Posted by: Anuradha at January 12, 2007 4:13 AM

How can I have the entire Pre-Portem analysis.

Posted by: Arthur May at November 10, 2007 6:47 AM

Hi Arthur, not sure what you are asking for. Can you please expand a little on your request?

Posted by: Shawn Callahan [TypeKey Profile Page] at November 10, 2007 1:28 PM

In a way, it's very similar to risk-anlysis process. A brainstorming in which risks are assembled, analyzed, ranked, and then bing tracked.
How do you define the difference?

Posted by: Joseph at March 14, 2008 5:05 AM